Sources and evidence register

Access date: 1 November 2026. Each source retains its publication and observation dates. The register distinguishes original statements, research and secondary reporting. Linked pages may change after this edition.

C1 — Number of Data Centers by Country (November 2025)

Cargoson (Cloudscene) · Updated 4 January 2026; underlying snapshot November 2025

Secondary page

Open source

Directory listings, not confirmed current operations. Source regional totals/geographic groupings are inconsistent; only individual country rows used.

C3 — The Chinese AI Infrastructure Boom: Introducing the SemiAnalysis China Datacenter Model

SemiAnalysis · 2026-09-25

Original research introduction; underlying proprietary dataset not accessed

Open source

Research model, not audited operating IT load. Product page describes 24 GW+ by end-2026; timing ambiguity retained.

C5 — Exclusive: Data Center Cancellations Top $260 Billion in 2026

Heatmap News · 2026-10-06

Secondary / market intelligence

Open source

Announced values likely undercount; not capital already spent and lost

C7 — Deepening our investment in Richland Parish Louisiana

Meta Data Centers · 2026-07-13

Primary announcement

Open source

Announced regional investment includes related infrastructure not solely buildings; status under construction from ground broken Dec 2024 and continued activity

C8 — Oracle Q1 FY27 earnings / Epoch AI profile / secondary

Oracle / Epoch AI / secondary · 2026-09-10

Secondary / research directory

Open source

Epoch interpretation and projection, not primary confirmation of all power bases. Unverified 1.2 GW site-power figure removed from this edition.

C9-cost — Datagrid starts Southland $3.5b data centre works

B2B News NZ · 2026-08-18

Secondary

Open source

Reported estimate; phase scope and verified spending not established; no USD conversion

C10-phase — ₹30,000 Crore For 400 MW; Inside Adani’s Massive Google AI Data Centre Bet

Outlook Business · 2026-08-07

Secondary reporting of earnings call

Open source

Secondary management reporting, estimated construction cost excluding GPUs; overlaps Google programme; do not add

C4 — North America Data Center Trends H1 2026

CBRE · 2026-08-27

Primary industry report

Open source

Colocation/wholesale available capacity across eight primary markets only; does not measure GPU utilisation or profitability

C12 — Project Suncatcher prototype satellite is in orbit

Google Research · 2026-10-01

Primary

Open source

Research test payload, not a commercial orbital data centre

C9 — Horizontal works begin on Datagrid’s AI data centre campus in Makarewa

Datagrid · Release dated 18 August 2026; page labelled 19 August

Primary operator statement for works; secondary reporting retained separately for cost

Open source

Initial works only; not completed data halls or operating capacity

Operator project overview — planned 280 MW capacity

C10 — Our First AI Hub in India, Powered by a $15 Billion Investment

Google · 14 October 2025

Primary programme announcement; phase estimate retained separately as secondary

Open source

Broader programme; not spent capital or a single phase construction bill

C6 — Financing the AI buildout

Brookings / research by Stijn Van Nieuwerburgh · September 2026 conference research

Research publisher summary

Open source

Buildings, power, networks and equipment included; forecast not audited spending or overspend

C12-response — First response from Project Suncatcher prototype satellite

Google Research · 30 October 2026

Primary company research announcement

Open source

Research demonstration, not commercial-scale service

C10-groundbreaking — Google Breaks Ground on India AI Hub

Adani · 2026-04-28

Primary partner announcement

Open source

Groundbreaking confirms announced commencement, not completed operating capacity

Capacity-model timing caveat

The original introduction and model product page use different timing language for the China fleet. Read the model product page. This ambiguity is not resolved by the review.

Datagrid project capacity

The works announcement does not contain every project specification. The planned 280 MW figure is described on the operator project page.

Download the retained records

Help keep this research open

Voluntary contributions help fund research, source access, hosting and updates, so our published findings and evidence tables remain freely available to the public.

Contributing does not buy a particular conclusion, editorial control or priority. We will report how research contributions are used.

Support open research through PayPal — opens PayPal in a separate tab.

Contributed and have a research suggestion?

Use our contact form to share your proposed topic, questions, countries or sources. If you would like us to associate your suggestion with a contribution, include your PayPal transaction ID or receipt reference, payment date, amount and currency. Providing a payment reference is optional. These details remain private.

Suggestions help guide future research. Contributions do not guarantee that a topic will be undertaken, buy priority or determine our findings. You are also welcome to suggest research without contributing.

Contributions and AI assistance

Research compiled by Grok under instruction from John A Brown, The Blue•Print Research Unit. Editorial integration and source checks used ChatGPT assistance at John’s direction.

The original question and scope came from John. AI assistance produced drafts, tables and website code and helped check cited sources. John approved publication of this edition. Checking cited material is not independent verification of underlying claims.

Publishing Contributions Specification — Draft 0.1 · Publishing Contributions Registry

Published contribution statement — revision 1 · Download contribution statement as XML

Registry reference: PCR-20261031-7A5A82E2E9157692DF3F3DDA. This is a registrant declaration, not independent verification or endorsement of the research.